Around Maury, Maury County, Tennessee

What's Going Up

Oct. 17, 2026 Columbia

Spring Hill will fund $12 million to tie into Columbia's wastewater system

Spring Hill will pay for all of a $12 million project to send some of its wastewater to Columbia for treatment. $9 million connects Spring Hill's system to Columbia's, and the other $3 million upgrades Columbia's Carter's Creek Pike Pump Station. Columbia will take 500,000 to 1.5 million gallons a day once its new treatment plant, due in 2027, and the pump station work are done. Spring Hill is expected to pay Columbia $21 million to $62 million over 10 years, depending on how much it sends.

Source: City of Columbia News Flash